03.09 Key Component Selection: Five-Dimension Decision ​

Governance metadata | Owner: Head of Supply Chain | Last reviewed: 2026-10-22 | Next review: 2027-01-31

Core principle: only 5~10 parts in a piece of hardware truly decide whether it lives or dies. Key components such as the main SoC, sensors, motors, batteries and optics, once chosen badly, turn every later effort into debt repayment — costs that will not come down, certifications that cannot be cleared, and products discontinued half a year after mass production. This document sets out the identification criteria for key components and the five-dimension decision model, turning component selection from "engineer preference" into a decision that can be reviewed. Cost reverse-engineering: see 02.08; dual-sourcing switchover: see 03.06; tooling validation: see 03.01.


1. Why Component Selection Deserves Its Own Document ​

Our existing supply-chain interfaces are split by responsibility, but one link is missing:

DocumentWhat it coversWhat it does not cover
03.01 Tooling EngineeringHow to tool the structure and how to accept itWhich components go inside
03.02 Contract Manufacturing ControlWho manufactures for us, commercial terms and yieldWhich parts to select
03.06 Dual SourcingHow to cut single-point riskWhether to select it in the first place
03.07 SQEHow incoming quality is managedWhy this part was chosen
03.09 (this document)Which parts to select, and on what basisHow to manage them afterwards

Three kinds of debt you pay for choosing a key component wrong:

CostSymptomLatest point of detection
Cost debtHigh unit price / low integration / extra peripheral circuitry requiredVisible as soon as mass production starts; no way back
Compliance debtRF / energy efficiency / materials fail target-market certificationOnly surfaces at the T-6M certification sample submission
Supply debtDiscontinuation, longer lead time, no substituteBlows up 6~12 months after mass production

Of the three, supply debt is the most expensive: it hits after you have already loaded inventory and pushed product through the channel. That is exactly the origin of the "red single point" in 03.06, and the source must be stopped at the selection stage.


2. What Counts as a Key Component: Four Identification Criteria ​

Not every part number needs a five-dimension review. Screen with these four criteria; meeting any two of them makes a part a key component:

#CriterionDeciding question
1Cost shareDoes the part account for ≥ 5% of the BOM?
2Performance-determiningDo its specifications directly determine the core selling point?
3Compliance constraintDoes it involve mandatory certification for RF / energy efficiency / battery / materials?
4Supply riskIs the lead time > 8 weeks, or is the manufacturer's lifecycle < 5 years?

Typical key component list (by category):

CategoryCommon key components
Smart imagingMain SoC, image sensor, optical lens group, storage
Cleaning robotsMain controller, LiDAR / vision module, motors, battery pack
Energy storageCells, BMS controller, inverter module, connectors
WearablesMain controller, biosensors, battery, display
AudioMain controller, Bluetooth module, amplifier, speaker units

3. The Five-Dimension Decision Model ​

Score every key component across five dimensions. The weights are not fixed — they depend on the category, but they must be stated explicitly.

DimensionWhat is reviewedData source
PerformanceWhether it meets the core specifications; whether the margin is sufficient (recommended ≥15%)Specification sheet, measured samples
CostUnit price + peripheral circuitry + processing difficulty + yield loss, i.e. the total cost02.08 Teardown, distributor quotes
SupplyLead time, MOQ, manufacturer longevity commitment, capacity elasticityManufacturer / distributor, 03.06
ComplianceWhether target-market certification has been passed; whether remediation is required07.02 Wireless Market Access
SubstitutabilityWhether a pin-to-pin or firmware-level substitute exists; switching cycleManufacturer roadmap, substitute-part qualification

Scoring Criteria (Example; Adjust Weights by Category) ​

Dimension1 point3 points5 points
PerformanceBarely meets specMeets spec with 15% marginMeets spec with 30%+ margin
CostHighest total costMedianLowest total cost with high yield
SupplySingle source, lead time >16 weeksDual source, lead time 8~16 weeksMultiple sources, lead time <8 weeks
ComplianceNot certified, remediation requiredCertification in progressTarget-market certification passed
SubstitutabilityNo substituteSubstitute exists but needs board changespin-to-pin, drop-in replacement

Discipline: scoring exists to surface disagreement, not to compute a single right answer. If any dimension scores 1 point, you must write down "the reason for accepting the risk + the closure plan + the owner"; otherwise the part may not enter 01.08 GR2.


4. Component Selection Decision Matrix (Template) ​

⚠️ The value columns must be filled in from measurements; scores must be jointly confirmed by the review board and never entered by a single person.

CandidatePart numberPerformanceCostSupplyComplianceSubstitutabilityWeighted scoreVetoDecision
A
B
C
Weight—100%

Decision record (mandatory fields):

ItemContent
Selected option
Rejected options and reasons
Residual risk accepted
Risk closure plan and owner
Re-review trigger conditions(Price increase / longer lead time / discontinuation notice / certification failure)

5. Hard Disqualifiers (Non-Negotiable) ​

If a candidate meets any one of the following, it is eliminated outright; no management exception is accepted:

  • [ ] The manufacturer's longevity commitment is < 5 years (or it is in EOL/NRND status)

  • [ ] The key component is single-sourced with no substitution path (red-line single point, see 03.06)

  • [ ] Target-market mandatory certification has not been passed and there is no clear remediation path

  • [ ] Lead time > 16 weeks with no backup capacity

  • [ ] The part involves controlled items and export-control screening has not been completed (see 07.12)

This sits alongside the double-blind circuit breaker in 01.07 GR1 — "BOM ≤ 30% MSRP + PCB area ≤ 85% stacking limit". Those two rules govern the total, while this one governs the individual part.


6. Interfaces with Adjacent Documents ​

02.08 Teardown reverse engineering → Learn which parts competitors use and at what cost
        ↓
03.09 Component selection (this document) → Decide which parts we use
        ↓
03.01 Tooling / DFM → Whether the structure fits them and whether they are buildable
03.02 Contract manufacturing → Who builds it and at what yield
03.06 Dual sourcing → Where the second source for that part is
07.02 Certification → Whether that part can pass certification
        ↓
01.08 GR2 tooling and lock-order → Selection conclusions enter the risk list

Interface rules:

RuleExplanation
Teardown before selectionWithout benchmarking from 02.08, selection is nothing but engineer preference
Selection before toolingFreezing key component specifications is a precondition for the T0 trial mold in 03.01
Dual sourcing follows selectionThe second source must be defined at the same time as the key component is selected, see 03.06
Certification follows selectionFor parts with compliance constraints, the certification schedule starts during selection, see 07.02

7. Common Mistakes ​

MistakeConsequenceCorrection
Judging unit price only, ignoring total costPeripheral circuitry and yield losses eat back the savingsUse the total-cost basis
Judging performance only, ignoring lifecycleDiscontinued half a year after mass production, forcing a board redesignRequest the manufacturer longevity commitment letter
Picking niche parts for differentiationLong lead time, no substitute, poor ecosystemPrefer mainstream parts for key components
One-person decisionNobody reviews the riskReview board + decision record
Ignoring compliance constraintsT-6M certification failure, launch delayStart certification during the selection stage
Thinking about the second source only after selection is doneThe switching cycle cannot be metDefine dual sourcing together with selection

Execution Checklist ​

  • [ ] Key component list identified: screened with the four criteria, meeting any two of them

  • [ ] Five-dimension weights stated by category: performance / cost / supply / compliance / substitutability

  • [ ] Total-cost basis applied: includes peripheral circuitry, processing difficulty and yield loss

  • [ ] Longevity commitment obtained: stamped document from the manufacturer or a tier-1 distributor

  • [ ] Compliance constraints confirmed: target-market certification status and remediation path

  • [ ] Substitution path defined: pin-to-pin or firmware-level, with the switching cycle estimated

  • [ ] Hard disqualifiers checked one by one: all 5 passed

  • [ ] Decision record completed: rejection reasons, residual risk, closure plan, owner

  • [ ] Re-review trigger conditions set: price increase / lead time / discontinuation / certification failure

  • [ ] Conclusions entered in the GR2 risk list: see 01.08