03.06 Supply Chain Dual Sourcing and Supply-Disruption Switching Playbook ​

Governance metadata | Owner: Head of Supply Chain | Last reviewed: 2026-10-22 | Next review: 2027-01-31

Core principle: single-source supply is the hidden total-loss risk of hardware overseas expansion. Dual sourcing is not "two names on a list" but certification, tooling, materials, inventory, and switching cost being executable within 30–60 days. This document provides the default playbook for identification, triggers, switching, finance, and post-mortem review. Contract manufacturing commercial terms: see 03.02; quality traceability: see 03.07.


1. What Counts as Real Dual Sourcing ​

TierSingle-source riskSwitchable dual source (minimum bar)Acceptance evidence
Whole-unit contract manufacturingOnly 1 ODM1 primary + 1 backup; backup factory passes trial tooling / small batchBackup factory small-batch report
Critical modulesOnly 1 supplier (optics / battery / motor)≥2 suppliers passing key DVT itemsDVT report + difference table
Core part numbersSingle chip/sensorpin-to-pin or firmware adaptation + safety stockAlternate part approval form
ToolingOnly 1 set locked in one factoryDual cavity / spare cavity, or ownership can be transferred outTooling ownership and transfer-out SOP
CapacityA single line at full loadBackup line can start within 4 weeksCapacity reservation agreement

Red single points: critical path + no alternative + lead time > 8 weeks → must be entered into the GR2 risk list at [01.08], with an owner and a closure date assigned.

Red Single-Point Scan Table (Template) ​

Material/moduleSingle sourceLead time (weeks)Switching cycleSafety stock (days)OwnerClosure plan
Main SoCYes2012+15Supply ChainMaterial preparation / alternate qualification
Battery packYes10820HardwareSecond cell DVT
Main toolingYes1414—StructureOwnership + transfer-out
Packaging printingNo3230PackagingDual-factory rotation

2. Supply-Disruption Trigger Tiers ​

TierTriggerResponse deadlineCommanderParallel actions
P0Primary factory shutdown / EOL / withheld goods creating a stockout risk > 4 weeks24h war room; 72h switching planGTM operatorCustomer complaint contingency 07.05, tariff path 07.08
P1Yield collapse, 2 consecutive weeks of missed delivery72h assessment; 2 weeks to lock the backup sourceSupply Chain AUpdate the 03.05 light
P2Logistics issue / brief shutdown1 week to expedite + raise inventoryPlanning managerIf channel commitments are unchanged, escalate to P1

3. Switching Decision Tree (Default) ​

Supply-disruption signal
  ├─ Does it affect shipments in the next 30 days?
  │    ├─ No → Expedited logistics + raise safety stock (03.05 light color)
  │    └─ Yes ↓
  ├─ Has the backup source already been certified to the same spec / small batch?
  │    ├─ Yes → Lock capacity → Tighten IQA → Communicate delivery dates to channels
  │    └─ No ↓
  ├─ Can certification / mold modification be completed within 30 days?
  │    ├─ Yes → Conditional: limited pilot production + reduce channel commitments
  │    └─ No → No-Go: stockout PR + postponement / SKU reduction (07.05)

Financial red line (default): If the switch drives Landed Cost +>5% or BEP +>15% → return to 01.08 / Finance; sales are forbidden to promise the original price and original delivery date without a signed approval.

Certification red line: A backup source lacking mandatory certification (FCC/CE/BIS etc. 07.02) must not pass off "engineering samples" as mass production.


4. Switching Execution Playbook (By Day) ​

DayAction
D0Stand up the war room group; freeze new channel commitments
D0+1Confirm backup source capacity window; BOM difference table
D0+3First-batch inspection standard (AQL one level tighter); packaging / labeling
D0+7Finance scenario into 07.06; cash validation 07.07
D0+14Written delivery date update to channels; MAP unchanged
D0+30Post-mortem review: yield, customer complaints, dead stock, cost variance

5. Default Inventory Policy (Connected to 03.05) ​

Material typeRecommended safety stockNotes
Long-lead-time chips≥15 days + 1 order windowDouble until dual sourcing is complete
Structural parts≥20 daysHigher when the tooling is single-sourced
Packaging≥30 daysLower if it can be localized

The single source of truth for DOS light colors: 03.05.


6. Switching Checklist ​

  • [ ] Primary/backup BOM and firmware difference table (permitted differences signed)

  • [ ] Backup source safety and reliability certifications within their validity period

  • [ ] Tooling ownership and transfer-out proof

  • [ ] First batch IQC tightened + aging

  • [ ] Channel talking points; MAP unchanged

  • [ ] Cost variance into the 07.06 scenario

  • [ ] Cash: switching prepayment vs 07.07

  • [ ] Certification coverage confirmed (07.02)

  • [ ] 30-day post-mortem review meeting booked



8. Switching Cost Breakdown (Feeds Finance) ​

Cost itemMagnitude referenceOne-off
Backup source certification / testingPer projectYes
Mold modification / fixturesPer projectYes
Air freight replenishmentFreight rate differencePhased
Resident engineersPerson-weeksPhased
Unsold primary-source inventoryBook valueRequires a disposal plan

All of it enters the 07.06 scenario; prepayments enter 07.07.

9. Communication Template Essentials (Channels) ​

  • Promise only "no later than date X" or a "phased delivery schedule"
  • Never promise "never out of stock"
  • Compensation is limited to the signed SLA

10. 30-Day Post-Mortem Metrics ​

MetricTarget
Backup source first-pass inspection yield≥ primary source steady state − 5pt
Customer complaint rate≤ 1.2× the pre-switch level
Actual landed cost variance≤ model + 2pt
Unsold primary-source inventoryWritten disposal plan in place

11. Single-Point Heat Map (Example; Must Be Filled Per Product) ​

ModuleSupplier countGeographic concentrationPower / strike riskOverall
SoC1HighMediumRed
Battery1MediumMediumRed
Injection-molded parts2LowLowGreen
Packaging2LowLowGreen

Red items go into the GR2 closure plan.

12. War Room Group Rules ​

  • Prohibited to commit delivery dates externally before the tier is assigned
  • All decisions @ a named person
  • Written update daily at 18:00 (if P0)

Post-launch supply disruption: GR4 Conditional can be bundled with "reduce SKUs to protect delivery", avoiding heavy advertising with no stock in hand.

14. Post-Mortem Report Structure ​

  1. Timeline
  2. Root cause
  3. Switching cost actual vs model
  4. Customer complaints and channel impact
  5. Systemic improvements (contract terms / inventory / dual sourcing)

16. Industry Comparison: Which Categories Have More Red Points ​

CategoryCommon red points
Energy storageCells + BMS
Lawn mowersRTK / motor
TelescopesOptical module
TWSController + battery

17. Key Dual-Sourcing Contract Clauses ​

  • Minimum capacity guarantee or priority supply
  • Tooling ownership
  • Prohibit exclusivity that locks out the backup source (legal review)

18. Drill Script (P0 Half-Day) ​

TimeAction
0hSimulated shutdown notification
+1hRed point confirmation and tier assignment
+2hBackup source capacity confirmed by phone
+4hFinance impact table draft
+6hChannel talking points finalized

High-ASP projections must include the 03.06 page, otherwise the story is incomplete.

21. Switching Cost Fill-In Table (Feeds 07.06/07.07) ​

Cost itemAmountOne-off / recurringOwner
Backup source certificationOne-offHardware
Mold modification / fixturesOne-offStructure
Air freight replenishmentPhasedLogistics
On-site supportPhasedSQE
Primary-source dead stock disposalOne-offFinance
Total peak incrementFinance

Peak increment > 20% of the cash buffer → escalate to the GTM operator for approval.

22. Communication Matrix (Who Says What, and When) ​

AudienceWhen (P0)ContentProhibited
ChannelsWithin 24hDelivery impact + phased delivery table"it's fine, no impact"
Customer serviceWithin 24hUnified talking pointsFrontline private promises
Investors / boardWithin 48hIf shipment guidance is affectedConcealing a major supply disruption
PublicOnly when necessaryLegal reviewSelf-congratulatory statements

23. Post-Mortem Closure Criteria ​

  • [ ] The root cause is not "the supplier suddenly" but has leading indicators

  • [ ] The red point heat map has been updated

  • [ ] At least one systemic change has been made to contract / inventory / dual sourcing

  • [ ] Actual vs model cost deviation <15% or has been explained